Subcontractor pursues payment dispute

A mechanical subcontractor entered AAA arbitration proceedings in connection with its $2 million payment dispute with a general contractor on a 930,000 square foot, $175 million LG manufacturing plant project on behalf of a Fortune 250 owner, including filing a mechanics' and materialmen's lien against the project property.

Waller represented the subcontractor and obtained a favorable settlement for the client through mediation after successfully compelling the state court action to arbitration and before arbitration evidentiary hearing.

Related Professionals

Related Services

Chris' Related Experience View More of Chris' Experience

National restaurant chain involved in payment and lien claims

Defended payment and lien claims brought by general contractors for several Southeastern locations of a national restaurant chain.

READ MORE

Contractor/developer prevails in arbitration following dispute with electrical subcontractor

Represented a high-profile real estate developer in a costly dispute against an electrical subcontractor. The matter was settled following arbitration.

READ MORE

HCA negotiates updates Suite of Design and Construction Agreements

Advised HCA Healthcare, Inc. in the update of its suite of design and construction agreements.

READ MORE

General contractor defends payment claims related to Nashville hotel project

Defended an ENR 250 general contractor in state court and AAA arbitration proceedings against payment claims brought by a glazing subcontractor in connection with a high-end, 450-room hotel project in downtown Nashville, Tennessee. The case ended successfully via mediation.

READ MORE

Healthcare owner defends against payment claims on project

Defended a Fortune 500 healthcare owner against payment claims and construction lien asserted by a project's general contractor after the healthcare owner had delay, defective work and excessive costs claims related to the project. The claims were resolved favorably through mediation and the project was completed.

READ MORE

Custom homebuilder sues for unauthorized copying and use of blueprints

Represented a custom homebuilder in intellectual property claims against a competing homebuilder related to the unauthorized copying and use of the homebuilder’s registered floorplans and blueprints for its custom home designs. Settled the matter favorably.