National restaurant chain involved in payment and lien claims

A national restaurant chain was involved in a construction dispute stemming from the restaurant owner's defect and delay claims, and payment/lien claims filed by the general contractor and subcontractors.

Waller counseled our client throughout the completion of the project and during the claims process, settling the dispute prior to trial. Waller continues to defend and prosecute similar construction-related claims for the restaurant chain for their various project locations across the U.S.

Chris' Related Experience View More of Chris' Experience

Subcontractor pursues payment dispute

Served as lead counsel to the subcontractor and worked to win a favorable settlement.

READ MORE

Contractor/developer prevails in arbitration following dispute with electrical subcontractor

Represented a high-profile real estate developer in a costly dispute against an electrical subcontractor. The matter was settled following arbitration.

READ MORE

HCA negotiates updates Suite of Design and Construction Agreements

Advised HCA Healthcare, Inc. in the update of its suite of design and construction agreements.

READ MORE

General contractor defends payment claims related to Nashville hotel project

Defended an ENR 250 general contractor in state court and AAA arbitration proceedings against payment claims brought by a glazing subcontractor in connection with a high-end, 450-room hotel project in downtown Nashville, Tennessee. The case ended successfully via mediation.

READ MORE

Healthcare owner defends against payment claims on project

Defended a Fortune 500 healthcare owner against payment claims and construction lien asserted by a project's general contractor after the healthcare owner had delay, defective work and excessive costs claims related to the project. The claims were resolved favorably through mediation and the project was completed.

READ MORE

Custom homebuilder sues for unauthorized copying and use of blueprints

Represented a custom homebuilder in intellectual property claims against a competing homebuilder related to the unauthorized copying and use of the homebuilder’s registered floorplans and blueprints for its custom home designs. Settled the matter favorably.